PROJECT

Nittan Valve Headquarters and Factory

In this project, we supported the realization of the construction of facilities without stopping the manufacturing lines in operation, despite the limited site area in the reconstruction of the head office plant of Nittan Valve.


Project Issues


Nittatsu Valve was planning to rebuild its aging headquarters plant. The site was densely populated with factories. The site is densely populated with factories, and the company was faced with the difficult task of dismantling and building a new main factory without stopping the production line. The client wanted to build a facility that would meet earthquake resistance and other standards without stopping production, and within budget.

 

Index Consulting Solution


Building a new headquarters plant without stopping the production line in operation Because we needed to build a new headquarters plant without stopping the production lines that were already in operation, we adopted a "stay-at-home" construction method, leaving the existing headquarters plant in place and building a new plant outside of it. The new plant was built on top of the existing plant, and after the new plant was completed, the old plant on the inside was dismantled. In order to realize this method and to proceed with the construction on schedule, it was necessary to explain the construction process and risks to the government and obtain permission.

 

For the reconstruction of the head office, in order to secure office space during construction, temporary offices were set up in existing factories and other locations to support the smooth execution of duties during demolition and construction. In addition, because it was necessary to listen to the requests of all related parties and build consensus, Index Consulting formed a project team within Nittan Valve, which was responsible for organizing regular meetings and facilitating the meetings.

 

Index Consulting formed a project team within Nittan Valve, which was responsible for organizing regular meetings, facilitating meetings and supporting the smooth promotion of the project.

 

Index Consultinghas been realized


As per the client's request, we were able to build a new head office plant without stopping the production line in operation. As requested by the client, we were able to build a new head office plant without stopping the production line in operation. We were also able to reduce the overall cost of the project without compromising functionality. Through careful negotiations, we were able to meet the construction schedule without any delays due to disagreements with the government.

 

Other projects|Search by building use and solutions

CONTACT

03-6435-9933

Contact Us
CONTACT